However, if and to the extent that the Engineer’s failure was caused by any error or delay by the contractor, including an error in, or delay in the submission of, any of the contractor’s Documents, the Contractor shall not be entitled to such extension of time, Cost or Profit.
1.9
业主要求的错误
/Errors in the Employer’s Requirements/(YB)
If the contractor suffers delay and/or incurs cost as a result of a an error in the Employer’s Requirements, and an experienced contractor exercising due care would not have discovered the error when scrutinizing the Employer’s Requirements under sub-Clause 5.1 GENERAL DESIGN OBLIGATIONS, the Contractor shall give notice to the Engineer and shall be entitled subject to sub-Clause20.